Rio2 reported that construction at Fenix Gold reached 63% in Q3, showing strong momentum as it remains on schedule and on budget for first gold in January 2026.
Progress accelerated across key areas, including leach pad extensions, ADR plant work, and ore stacking, positioning the project for commissioning.
With gold prices rising dramatically, Rio2 is nearing a key inflection point as it transitions to production and begins generating heavy cashflows.